IMG_7328
IMG_7399
IMG_6809
IMG_7335
IMG_7327
IMG_6473
IMG_6445
IMG_6033
IMG_5980
IMG_5776
IMG_6007
IMG_5882
IMG_5764
IMG_5515
IMG_5496
IMG_5456
IMG_5717
IMG_5690
IMG_5689
IMG_5546

muller street, redland bay - residential development

MPN Consulting for Harridan Pty Ltd

Redland Bay, Qld

$3.7 million

In late 2016 ALLROADS began construction of a 64-lot boutique development, Vanstone Park, in Redland Bay.   

 

Specific works undertaken included significant clearing, earthworks, stormwater, sewer, roadwork, water reticulation, detention basin construction and retaining walls.

 

Providing a challenge to the project was the fact that the site was divided in two via an existing waterway; with separate entrances each side of the estate being required.

 

Subsequently, environmental management was a critical aspect to the project with four different species of turtles living in the waterway and the existing bushland home to a variety of wildlife,

 

A fauna spotter/catcher was engaged to relocate existing wildlife (Wallabies and Lizards) and over 40 turtles. In addition, work arounds were put in place to ensure the protection of vegetation and comprehensive erosion and sediment controls were put in place to protect the waterway.

 

Through the effective execution of the detailed environmental management plan, ALLROADS were able to deliver all works within the time frame, to budget and most importantly without damaging areas of protected vegetation or harming any fauna.

  • Carried out more than 16,800m3 of cut to fill bulk earthworks operations and imported 31,000m3 of fill

 

  • Construction of over 2,100m2 concrete sleeper retaining walls and 550m2 of ‘A’ grade boulder wall

 

  • Construction of over 5,800m2 pavement with asphalt surfacing including speed platforms.

 

  • Placed 850m2 of exposed aggregate driveway and 1,300m2 of footpath.

 

  • Installation of sewer and water reticulation infrastructure (two separate system/circuit).

 

  • Construction of two separate stormwater drainage structures, including landscaped open channel drains, bio-retention basins and a triple cell 1.5m x 0.9m box culvert with two 2.2m link slabs.

 

  • Placed 700m2 of rock pitching.

  • Grey Facebook Icon
  • Grey LinkedIn Icon
  • Grey Instagram Icon