Granite Creek South Bound Overtaking Lanes

ALLROADS were awarded the contract to undertake Road Widening works on the Bruce Highway at Granite Creek.

Works undertaken for the Road widening and construction of the southbound overtaking lane and include; Earthworks, drainage, unbound and stabilised pavement, surfacing works and new road furniture and road signage.

As the works are constructed under live traffic conditions, a Traffic Management plan was developed to limit the required traffic switches to just 3 stages.  This will reduce driver confusion when travelling through the site.  

Careful programming and strategic staging is integral in order to ensure a safe and trafficable site is maintained throughout the construction duration.

Stakeholders, including Local Government and Local residents / Land owners are consulted in accordance with our Community Liaison and Traffic Management Plan requirements.

 

Safety is maintained at all times in accordance with ALLROADS Safety Management System procedure and Policy.  

ALLROADS’ effective and innovative project and QHSE management approach will enabled the project to be completed as per the schedule.

  • Stormwater Pipe jacking 750 RCP

  • Construction of 5/2400×900 RCBC

  • Pavement stabilisation at 2% GB Cement

  • 21,500m3 of cut to fill Embankment

More Projects

Ballin Drive Detention Basin Construction

Previous Next Toowoomba Regional Council $3.0 million Centenary Heights, QLD The Ballin...

Read More

DTMR Bruce Highway Safety Program – Pine River

Previous Next Department of Transport and Main Roads $4.3 Million Bruce Hwy...

Read More

Kolonga Street, Woodridge Master Drainage Project

Previous Next Logan City Council $1.8 million Woodridge, Queensland ALLROADS were awarded...

Read More