federation drive rural reserve

Jeteld Pty Ltd ATF Clive Berghofer Developments

Highfields, Qld

$2.4 million

In late November 2018 ALLROADS commenced Stage One works on the Federation Drive Rural Reserve, a 29 lot residential subdivision project.

‚Äč

This first stage of works involved construction of new access roads from Steinberg Road, eventually connecting onto local residential streets (Denaid Street, Griffin Street and Federation Drive).

 

Works performed under the contract included earthworks, stormwater, electrical and water reticulation, a 15,000m2 drainage basin and surfacing works. 

 

ALLROADS maintained the work site with excellent feedback from our Client and Council representatives, praising the general site appearance, quality and timeliness of works.

 

Throughout construction ALLROADS faced the challenge of having a 100,000m2 exposed site during an extremely dry period. Therefore, the team prioritised the implementation of dust control measures to minimise the impact to surrounding residents.

 

A detailed Project Management approach was implemented to ensure the desired outcomes were achieved and the project was completed within the specified time frame and allocated budget.

  • 33,000m3 of cut to fill

 

  • 1,100m of watermain installed

 

  • 1,200m stormwater lines laid

 

  • 11,000m2 of turf laid  

 

  • Over 650t of asphalt

 

  • Environmental Management