20180808_101536
20180808_101453
20180808_101518
IMG_8288
IMG_3507
20180531_092029
20180531_094743
20180531_094654
IMG_8405
20180531_112100
IMG_20180525_1448201
20180604_101346
IMG_5048
IMG_6269
10.01Dayboro3
IMG_8741
IMG_7487
IMG_6297
Dayboro 3108

dayboro residential development

Dayboro Developments Pty Ltd

Dayboro, Qld

$5.2 million

Dayboro Development is a multi-stage residential development located along Fingerboard Road and Hay Road.

 

ALLROADS commenced bulk earthworks on the initial Stage One contract in late August 2017, with Stages Two and Three following in 2018.

 

Works across all stages included: external water main, sewer pump station, external sewer rising main, Fingerboard Road upgrade and internal subdivision civil works including: drainage, sewer, water, services, roadworks, concrete works, retaining walls and bio-retention basins. 

 

Detailed planning and programming was implemented to ensure the project program was maximised, enabling the Developer to guarantee settlement of the lots as quickly as possible.

 

Demonstrating ALLROADS' innovative construction methodology approach, we provided the client with an alternative for using Class B sandstone retaining wall blocks as opposed to Class A, saving the client approximately $40,000.

 

Working through the summer period proved difficult due to the large stormwater events which occurred.  ALLROADS undertook stringent third-party environmental verification of the environmental controls being implemented resulting in the controls, EMP and construction methodology itself being modified as required.  

 

Although not a contractual requirement, ALLROADS went above the legislative Environmental requirements to ensure complete compliance was maintained during the construction process, and as a result, Lake Samsonvale drinking water quality was not affected.

  • 110,000m3 cut to fill bulk earthworks

 

  • Fingerboard Road upgrade

 

  • Construction of over 1,300m2 concrete sleeper and 300m2 boulder retaining wall structures

 

  • Construction of over 10,300m2 new road pavements with asphalt surfacing

 

  • Installation of sewer and water supply infrastructure including a sewer pump station

 

  • External works sewer rising main and water main on Dayboro Road

 

  • Construction of 1.9km stormwater drainage infrastructure including two bio-retention basins

 

  • High level of erosion and sediment control due to highly sensitive Lake Samsonvale catchment region

  • Grey Facebook Icon
  • Grey LinkedIn Icon
  • Grey Instagram Icon