Allawah Road Realignment

Powerlink

Blackwall, Queensland

$2.9 Million

ALLROADS were awarded the contract to relocate the existing Allawah Road to allow space for the future extension of Powerlinks’ Blackwall Switchyard.

 

The scope of works included four sections: Preliminaries, Earthworks, Roadworks and Stormwater Drainage and saw the construction of over 750m of a new two-lane road. In addition a visual screening barrier was constructed to block out views from adjacent residents.

 

Due to the alignment of the road being subject to flooding, there was a requirement for the elevation to be in line with Brisbane City Council flood level requirements. To ensure this requirement was met, ALLROADS installed a number of major stormwater culverts.

 

Works also required strict environmental controls given the sites proximity to the Brisbane River and location within a Koala Habitat and therefore required close community liaison to minimise any impact to surrounding residences.

 

Through efficient and effective planning and a “hands on” project management approach, the works were completed on budget, to the specifications of Powerlink, Council and DTMR and ahead of schedule; with the original 16 week program of works being completed in just 12 weeks.

  • 55,000 m3 Bulk Earthworks

  • Roadworks included road lighting, 375 dia watermain, deep lift asphalt pavements, kerb and channel, subsoil drainage and stormwater pits

  • Significant community liaison

  • Major stormwater components including 1800x1800 3 cell culvert to DTMR Standards

  • Realignment of new 375 dia watermain and connections for QUU

  • Significant environmental controls given proximity to the Brisbane River and Koala Habitat Zone

  • Works also located in a cultural heritage zone

  • Works completed 4 weeks ahead of schedule.